Emergency reboot of data center network component
Scheduled Maintenance Report for Flying Circus
Completed
The scheduled maintenance has been completed.
Posted Jan 09, 2021 - 23:00 CET
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jan 09, 2021 - 22:00 CET
Scheduled
Our data center informed us that they experienced a disruption at a central network component (which also affected the redundancy layer) and that they will be performing an urgent reboot of the affected components tonight between 22:00 and 23:00 CET.

We are currently in touch to clarify whether this was related to minor timeouts we have seen for a few customers today around 16:35-16:40 and 17:55-18:05.
Posted Jan 09, 2021 - 20:20 CET
This scheduled maintenance affected: RZOB (production) (Network and Internet uplink).