Data center power maintenance
Scheduled Maintenance Report for Flying Circus
Completed
The scheduled maintenance has been completed.
Posted Mar 05, 2018 - 17:00 CET
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 05, 2018 - 07:00 CET
Scheduled
Our data center has informed us about upcoming maintenance:

* Maintenance of the power transformer
* Exercise a "black building test" where the data center will be disconnected from the power grid.

There will be no downtime.
Posted Jan 25, 2018 - 09:11 CET