Network infrastructure maintenance
Scheduled Maintenance Report for Flying Circus
Completed
We have finished the maintenance successfully.

While monitoring the situation closely we have seen 2 disruptions of ~70s for the frontend network and 1 disruption of the server-to-server network. Upgrades in our internal management network did not have customer-visible impact.
Posted May 06, 2021 - 21:44 CEST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted May 06, 2021 - 21:00 CEST
Scheduled
We are going to upgrade the NOS on a number of switches in our data center.

We expect up to 5 short service interruptions (less than 1 minute each). In case of unexpected problems we have a technician on premise to respond immediately.
Posted May 03, 2021 - 06:05 CEST
This scheduled maintenance affected: RZOB (production) (Network and Internet uplink).