Offsite / laboratory network UPS maintenance
Scheduled Maintenance Report for Flying Circus
Completed
The scheduled maintenance has been completed.
Posted Mar 17, 2022 - 14:00 CET
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 17, 2022 - 09:00 CET
Scheduled
Our previous yearly maintenance of the UPS in our offsite / laboratory data center indicated that a battery replacement is required which will be performed next Thursday.

We do not expect any interruptions.

In case of an unexpected local power outage during maintenance the following secondary services might be affected temporarily:

* Our emergency hotline will not be reachable during interruption.
* Emergency emails might be delayed.
* Customer specified service-checks (as shown on https://my.flyingcircus.io) will not be updated.
* Chat system rocketchat.flyingcircus.io
* gitlab.flyingcircus.io which may affect automated deployments
* hydra.flyingcircus.io which may affect automated deployments and system updates using "fc-manage"

We will also perform an "external maintenance bypass" procedure to verify proper emergency procedures.
Posted Mar 11, 2022 - 13:53 CET