Backup / Lab DC migration
Scheduled Maintenance Report for Flying Circus
Completed
We've finished switching the uplink successfully.
Posted Mar 21, 2023 - 08:40 CET
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 21, 2023 - 08:00 CET
Scheduled
We are continuing our Backup / Lab DC migration. This time the uplink connection within our build will be connected to a new fibre pair, which is expected to cause a few short downtimes in the range of a at most a few minutes.

As usual the affected services (Gitlab, Jenkins, Hydra, offsite monitoring) only secondary and will not impact customer traffic.
Posted Mar 17, 2023 - 16:51 CET
This scheduled maintenance affected: Central services and gitlab.flyingcircus.io.