Backup data center maintenance: UPS

Scheduled Maintenance Report for Flying Circus

Completed

The scheduled maintenance has been completed.
Posted Nov 03, 2026 - 15:00 CET

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Nov 03, 2026 - 08:00 CET

Scheduled

We will be performing maintenance on the UPS systems in RZHAL, our backup and laboratory data center, during this time.

We do not expect any interruptions to services, however in case of an unexpected local power outage during maintenance the following services might be affected temporarily:

* Our emergency hotline
* Emergency emails
* Customer-specified service checks (as shown on https://my.flyingcircus.io)
* Our Matrix chat
* gitlab.flyingcircus.io (which may affect automated deployments)
* hydra.flyingcircus.io (which may affect automated deployments and system updates using "fc-manage")

We will also perform an "external maintenance bypass" to verify proper emergency procedures.
Posted Nov 02, 2026 - 14:26 CET