Backup DC/Lab recabling
Scheduled Maintenance Report for Flying Circus
Completed
The scheduled maintenance has been completed.
Posted Feb 14, 2024 - 09:30 CET
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 14, 2024 - 08:30 CET
Update
We are postponing this maintenance until tomorrow morning, due to a short-term scheduling conflict.
Posted Feb 13, 2024 - 07:34 CET
Scheduled
We will be replacing a small number of cabling components in our lab and backup data center which will cause short interruptions (around 5 minutes) while replacing those components.

A few secondary services will be temporarily unavailable during this time, but no production services will be affected.
Posted Feb 06, 2024 - 08:30 CET
This scheduled maintenance affected: Emergency Channels (Hotline), gitlab.flyingcircus.io, and RZHAL (backup and development data center) (Network and Internet uplink).